Sections

About Us

 
Make a Donation
Local • Independent • Essential News
 

Experts say subdivision work damaged Hamilton Pool

Wednesday, May 14, 2008 by Austin Monitor

Outside consultants told Travis County Commissioners Tuesday that erosion and sediment control failures at a subdivision four miles upstream of Hamilton Pool in western Travis County led to more than $2.3 million in damage to the pool and its tributaries.

Hamilton Pool and its tributaries – Davis Creek, Cripple Creek and a number of smaller streams – are part of one watershed that contains about 1.8 million gallons of water that ultimately flows into the Pedernales River.

Last spring, a combination of failed construction controls on a proposed road and major rain events turned portions of the Hamilton Pool tributaries into a flowing river of mud. A report by Espey Engineering outlines the damage, which resulted, in some places, in silt that was six to eight feet deep in the creek bed.

Espey was brought in to assess the damage. In a discussion with Commissioners Court on Tuesday, consultant Victoria Harkins noted the damage from the construction and even a path in which the contractors drove across the creek bed.

“What we saw when we did the assessments of the creek bed and the draining tributaries is that the silt source is The Ranches (at Hamilton Pool),” Harkins told the commissioners. “I’m convinced, 100 percent, the silt source is The Ranches. There is a build-up of silt in areas along the creek that feed to Hamilton Pool of several feet. Layers of this silt cake the majority of this creek, and Hamilton Pool has a shelf of about five to six feet of silt along its bottom.”

Commissioners need to act fast because plants are beginning to grow in the displaced sand and silt. Harkins said the county had four options: no action; manual removal of the silt; manual removal of the silt and a wash down; or silt removal from Hamilton Pool, plus the filtration of the water.

The “no action” alternative would be a choice if commissioners wanted natural rain events to move the silt. Numerous rain events would be required to complete the job, said Harkins, who added it’s probably not possible to have a rain event large enough to scour Hamilton Pool itself, which would leave silt in the creek.

Commissioner Sarah Eckhardt asked Harkins what the impact would be if the county chose to move forward with that option.

“I believe that it will be a very long-term effect on Hamilton Pool,” Harkins said. “I believe that the silt shelf will stay there, it will stay cloudy and stay muddy and that during high use, individuals would create a muddy home, from people coming to swim.”

A second option would be the manual removal of the silt, with large amounts of sediment removed from the culvert areas and natural depressions along the creek. That sediment would be easy to recognize – the silt is a different color than the creek bed – and it could be easily removed.

The county also could combine that manual removal with a wash-down of the creek. The manual removal could remove large pockets of sediment and silt. A high-pressure spray could be used to wash down other areas. That spray would displace silt, which would be collected and removed.

If the county chose a full combination of options to restore the creek bed and filtrate the water and use vacuum trucks to remove silt from the bottom of the pool, the price tag could be upwards of $2.3 million. Such an effort would require running the vacuum pumps for a full 45 days to clear the water.

A small portion of the pool is in the Balcones Canyonlands Preserve, so a contractor would not be able to use heavy equipment during part of August, which is considered nesting season for endangered birds. Harkins recommended an initial creek clean-up, then additional filtration after nesting season.

County Judge Sam Biscoe said the court was not ready to make a decision. First, county leaders needed to figure out where the money will come from to complete a major clean-up project on Hamilton Pool.

“It may take a little time to amass $2.3 million,” Biscoe said. “So far, heavy praying by the County Judge hasn’t helped a whole lot. But we’ll keep working on that. We would make that decision, very soon. The source of funding…try to chat with those who are partners and those who should be partners and try to figure out a way to fix it. So we would expedite it to the extent possible, mindful of the BCP ramifications.”

You're a community leader

And we’re honored you look to us for serious, in-depth news. You know a strong community needs local and dedicated watchdog reporting. We’re here for you and that won’t change. Now will you take the powerful next step and support our nonprofit news organization?

Back to Top